The Changing look of West Broadway Ave. in Forest Lake

There’s been a flurry of construction progress on two fronts in Forest Lake this week. Crews lifted the bridge over SW 11th Avenue (CR-83) into place and have now turned their attention to the decking and on-off ramps. To the north on the Broadway Corridor Project, the intersection of Broadway and 4th Street has a new look as most of the trees had to come down. At 6th and Broadway on Monday, crews continue to work on installing underground storm sewer pipes. (Photo by Cliff Buchan, Forest Lake Times)

 